Implementation of installation and delivery of Khorram Abad metal frame

Implementation of installation and delivery of Khorram Abad metal frame

IN terminated
portfolio
Investor Name:
Published Date:
1970-01-01
Location:
Value:
Architecture:
About Project

Delivery time: 05/31/1401 Main client: Mapna Development 2 Second client: Fabco Description: 1- Installation of metal frame about 1,700,000 kg 2- Carbon steel welding operation about 1,800 meters 3- Moving parts from the depot to the work site 4- Installation About 27,514 bolts and nuts related to the structure