پایدار انرژی پایندان - خدمات مشاوره، طراحی، مهندسی، ساخت، تامین، نصب ، راه اندازی و بهره برداری

Enter your keyword

Get a quote

[mc4wp_form]

Installation and delivery of the metal frame of Unit 3 in Urmia

Installation and delivery of the metal frame of Unit 3 in Urmia

IN terminated
portfolio
Investor Name:
Published Date:
1970-01-01
Location:
Value:
Architecture:
About Project

Delivery time: 12/20/1401 Main client: Mapna Development 2 Second client: Fabco Description: 1- Installation of metal frame about 1,700,000 kg 2- Carbon steel welding operation about 1,800 meters 3- Moving parts from the depot to the work site 700 tons 4 – Installation of 27,574 bolts and nuts related to the structure